Oracle Planning and Budgeting Cloud Service (PBCS)

Project Charter Statement:

Implement an interactive, flexible, online budget and reporting system for the University that will facilitate a collaborative, streamlined, budget, planning and forecasting process that complements and enhances transparent data-driven decision making

Project Timeline

Stage Duration

Dates

Status

Initiate Requirements 3 weeks 11/17 – 12/15/17 Completed
Design 4 weeks (Extended to 10 total weeks) 12/18/17 – 2/23/18 Extended
Build 7 weeks 2/26/18 – 4/13/18 On time
Test 3 weeks 4/16/18 – 5/4/18 On time
Deploy & Close 2 weeks 5/7/18 – 5/18/18 On time

 

Detailed Project Timeline (Original)

Detailed Project Timeline (Revised 1/18/18)

 

Think Big We Do

Copyright © 2018 University of Rhode Island.